Melbourne-based Repurpose It is a recycling company with a difference: dedicated to making landfills a thing of the past, it is driven by the belief that all waste has the potential to be turned into value. To achieve its environmental mission towards a zero-waste world that respects earth’s natural resources, George Hatzimanolis (the CEO of Repurpose It), turned to CDE to transform construction, demolition and excavation (CD&E) waste along with contaminated railway ballast into in-spec sand and aggregate products that meet the requirements of the local building industry.

The first of its kind in Australia, the innovative wash plant sits on a 150-acre rehabilitated quarry site in Epping, a stones-throw away from Melbourne. With a portfolio of almost 2,000 materials wet processing installations globally, including C&D waste recycling plants that currently divert a total of 20 million tonnes of C&D waste worldwide every year, CDE was delighted to have designed this tailor-made materials recycling solution for Repurpose It. 

The Company

Repurpose It operates at the heart of Victoria state, the second most populated state in Australia. The company processes all types of waste from some of Australia’s largest local government authorities, private waste operators as well as local community members keen to make a positive difference.

The company offers a full-circle service to its clients, including waste management consulting, transport and collection and all other waste-to-resource processes. Its owner, George Hatzimanolis, leveraged his 15-year experience in the civil works to establish the resource recovery business in 2017 on the industrial ecology model.

Hatzimanolis’ core belief that action needs to be taken to stop the depletion of the world’s natural resources led him to focus on creating manufactured sands from waste, with a view to tackling contaminated materials with cutting edge technology, therefore deflecting the need for natural sand extraction.

Hatzimanolis recalls: “When putting the project together, the opportunities and projected results became clear. In recognition of our ‘best practice technology’ innovative approach and willingness to invest in industry-leading technology. Sustainability Victoria, a governmental body founded under the Sustainability Victoria Act 2005 to facilitate and promote environmental sustainability in the use of resources, issued us a grant of $500,000 for our project.

“We were delighted when integrated services company Downer, an existing CDE customer, came on board as a 50% partner in the business, ensuring a bright and sustainable future for Repurpose It.” 

The Challenge 

Victoria has the fastest growing demographics in Australia, with Melbourne alone totaling nearly 5 million of the state’s 6.5 million inhabitants. With the associated waste volumes continuing to escalate, the implementation of what is known as ‘industrial ecology processes’ is more than ever recognized as the only remedy to landfill pollution, where generated waste is collected, sorted and transformed into products fit for use in a variety of sectors.

The aim of the project was to develop a wet processing system capable of transforming a number of CD&E waste streams, including a majority of inert waste and some industrial waste previously earmarked for landfill for being too difficult to treat, including glass cutlet and drilling muds.

George Hatzimanolis explains: “Repurpose It is committed to recycling products at the end of their lifecycle to transform them into materials that will be used at the beginning of a new lifecycle. These include waste previously considered as impossible to process.

“To achieve 100% recycling of construction and demolition waste, we required a wet processing solution that could efficiently separate and wash every available fraction of material in the feed.” 

The Solution

C&D Waste Recycling Plant - Repurpose It - CDE

Daniel Webber, Regional Manager for CDE in Australasia, reflected: “Entrepreneurial companies such as Repurpose It, have identified that the Sydney Basin and Melbourne are running out of sand. The depletion of local sand reserves means that construction and concrete companies now have to cart sand via road from further away or turn increasingly to the production of manufactured sands from hard rock deposits which are more expensive to mine and more hard-wearing on plant and equipment.”  

“This is where C&D waste processing plants come into their own: they accept waste feed from metropolitan areas and clean it to repurpose it back into the local construction market.  At the same time, as there is limited room available for tailings ponds, our world-leading water recovery and tailings treatment technologies are used to make dry tailings that can be carted away or even turned into marketable products themselves.”

“Every CDE solution is designed with a zero-waste objective in mind, with constant innovation and patented products being developed to guarantee high-efficiency results with optimal water and energy savings whilst ensuring that pond footprint and maintenance, as well as plant downtime, is kept to a minimum.”  

Process Overview

The CDE solution at Repurpose It incorporates a selection of modular elements that work in synergy to produce the best results: an AggMax™ logwasher, the latest in the CDE patented Infinity screening range, a ProGrade H2-60 screen, an EvoWash™ sand classification & dewatering system, conveyors, a decanter centrifuge and an AquaCycle™ thickener.

The plant processes up to 150 tonnes per hour of a single waste input. Each single waste, depending on available volumes, will run for a minimum of two weeks. The feed material then changes to meet incoming waste types and volumes as well as production requirements. 

The AquaCycle™ Water Management System

AquaCycle Thickener - Water and Sludge Management - CDE

The C&D waste recycling wash plant operates as a closed loop system. Its efficiency is optimized by the incorporation of a wastewater treatment unit, a CDE AquaCycle™ thickener which allows the recycling of up to 90% of the wastewater for immediate re-use into the system. The process water, after passing into the deaeration chamber, passes gently to the center of the thickener so that the added flocculant can work and act on the sedimentation of the fine material.

A single motor operates the rack arms of the AquaCycle™ thickener for optimal treatment of the sludge prior to its drainage. As a result, every valuable grain of material is retained in the system.

Fine materials are trapped and the sludge is dewatered then expelled via the centrifuge to clean fill or landfill depending on the levels of contamination in the product. The wastewater is sent to the sewer under a trade waste agreement whereby it will ultimately be treated at the Western Treatment Plant with a view to recycling it for various applications.

With a capacity of 600m³/h, the AquaCycle™ thickener only requires a top up of 60m³/h and accepts water from street sweepings and educator truck dewatering pits, enhancing the project’s environmental objectives. Stormwater is used as a preferred option for top-ups and a portable water reserve is available as back up or to refill the plant after maintenance activities.

The precision of the CDE water management technology allows the washing plant to re-use the water to process different types of feedstocks, without any risk of cross-contamination or other diminution in the quality of the final materials.

When Footprint Matters

Key to the success of the CDE equipment is its modular make-up, allowing to associate compact processing modules within a small footprint without compromising on efficiency. As such, CDE equipment packs a punch even on the smallest sites, which is a substantial plus when it comes to recycling facilities located in urban settings.

Of significant importance to the Repurpose It project, effective sludge management by the centrifuge optimizes water recycling and efficiency of the system, reducing the need for large ponds.

The Result

C&D Wash Plant - Repurpose It Australia - CDE

The Repurpose It project perfectly aligns to CDE’s New World of Resource ethos and the company’s new plant processes up to 150 tonnes per hour of CD&E waste into high-value construction products every day, which would otherwise have been diverted to landfill.

The CDE tailor-made solution for Repurpose It takes C&D waste, rinses, and grades it to make six in spec products – 4 aggregates (4-10, 10-20, 20-150, 50-100 oversize) and two sands (0-2 and 0-4) – depending on feed available and its contamination levels.

Notably, Repurpose It operates a full circle process when the opportunity arises, such as in the case of the ongoing infrastructure project in Victoria which involves replacing level crossings: existing hydrocarbon-contaminated railway ballasts are washed, scrubbed to remove the contamination and the resulting recycle materials are re-used in the fabrication of new railway ballast.

The same applies for a new tunneling project: tunneling material is sent to Repurpose It for transforming and the transformed materials are re-used by the tunneling project as construction materials.  

A Crushed Carbon Footprint

Based on processing 500,000 tonnes of material through its innovative, state of the art CDE washing plant, Repurpose it can save more than 84,000 tonnes of CO2 every year.

George Hatzimanolis said: “This investment in CDE technology will prove to the world that we can achieve a zero-landfill objective and is a symbol of our unfailing commitment to protecting the planet by giving all waste a second life, a second purpose.

“Recycled sand and aggregates are now recognized as high-value materials of equivalent quality as materials processed from natural reserves. The CDE plant helps Repurpose It to achieve its goal of remaining a sustainable, ethical business that transforms transforming waste into re-usable products whilst having minimal environmental impact.”

Do you have a similar project to this? Get in touch today to see how CDE can help you maximize your return.